Question: TB MC Qu. 09-83 In an MRP problem, A is an MPS... In an MRP problem, Ais an MPS item. Every A requires 2 B's

TB MC Qu. 09-83 In an MRP problem, A is an MPS...
TB MC Qu. 09-83 In an MRP problem, A is an MPS... In an MRP problem, Ais an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. All initial Inventory values are O. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 500 in period 8. what will be the planned order release for Bin period 47 Multiple Choice 500 1,000 1.500