Question: TB MC Qu. 19-39 Given the following activity network: Given the following activity network: ded A2 BKO A1 A3 es Activity Al takes 5 weeks,

TB MC Qu. 19-39 Given the following activity
TB MC Qu. 19-39 Given the following activity network: Given the following activity network: ded A2 BKO A1 A3 es Activity Al takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time under the worst-case scenario, that is, A3 is late and takes 10 weeks? Multiple Choice 15 12 10 9