Question: Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination: Activity
Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination:
| Activity | Duration (days) | Immediate Predecessor(s) |
|---|---|---|
| A | 4 | - |
| B | 12 | - |
| C | 8 | - |
| D | 3 | A |
| E | 2 | C |
| F | 12 | B,D,E |
| G | 16 | D,E |
| H | 8 | F |
| I | 5 | G,H |
| J | 14 | I |
What is the overall duration of the project (in days)?
What is the earliest day you could start activity F? (Write the day number in the field below.)
What is the earliest day you could finish activity I?
What is the latest day you could start activity B?
What is the latest day you could finish activity C?
What is the slack time for activity D?
What would be the overall duration of the project if activity E were increased by 4 days, from 2 to 6 days?
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
ANSWER IS To calculate the answers to the questions we can use the Critical Path Method CPM for project management Ill provide the answers step by ste... View full answer