Question: The activities needed to develop a new software application are listed in the following table with the activity times and the order in which the

The activities needed to develop a new software application are listed in the following table with the activity times and the order in which the activities need to be performed:

ActivityDuration (weeks)Immediate Predecessor(s)
A5-
B8A
C5A
D7A
E5A
F8B,C
G13D,E
H7F,G


What is the overall duration of the project (in weeks)?


What is the earliest week you could start activity F? (Write the week number in the field below.)

What is the earliest week you could finish activity G?

What is the latest week you could start activity B?

What is the latest week you could finish activity A?

What is the slack time for activity D?

What would be the overall duration of the project if activity F were increased by 3 weeks, from 8 to 11 weeks?

What would be the overall duration of the project if activity B were increased by 4 weeks, from 8 to 12 weeks?

Step by Step Solution

3.47 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 The overall duration of the project in weeks can be found by identifying the critical path which is the longest path of activities from start to finish The duration of the critical path is the overa... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!