Question: Technical team can begin editing according document 1 5 days after they begin writing it what kind of dependency would this be represented as option
Technical team can begin editing according document days after they begin writing it what kind of dependency would this be represented as
option a start to start with a day lead
option B finish to finish with the day lead
option C start to start with day lag
option D finished to finish with day lag