Question: A technical team can begin editing of a large document 15 days after they begin writing it. What kind of a dependency would this be
A technical team can begin editing of a large document 15 days after they begin writing it. What kind of a dependency would this be represented as?
A. Start-to-start with a 15-day lead B. Finish-to-finish with a 15-day lead C. Start-to-start with a 15-day lag D. Finish-to-start with a 15-day lag