Question: Test Name: Start - a , b , c , d , e , f , g , h , Finish Duration: 0 days, 1

Test Name: Start - a, b, c, d, e, f, g, h, Finish
Duration: 0 days, 10.67 days?, 12.17 days?, 12.33 days?, 6 days?, 14.33 days?, 9.67 days?, 10.33 days?, 7.83 days? 0 days
Optimistic Duration: 0 days, 8 days, 11 days, 7 days, 6 days, 10 days, 8 days, 5 days, 4 days, 0 days
Expected Duration: 0 days, 10 days, 12 days, 12 days, 6 days, 14 days, 10 days, 10 days, 8 days, 0 days
Pessimistic Duration: 0 days, 16 days, 14 days, 19 days, 6 days, 20 days, 10 days, 17 days, 11 days, 0 days
Predecessors: 1,2,3,3,3,4,5,5,6,8,7,9
Project Model using MS Project
Given the project model above, and the simulation data table on the next page:
Calculate and identify the:
a) median duration
b) mean duration
c) probability of completing the project in less than 50 days
d) critical index for each activity
e) critical index for each path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!