Question: Test Name: Start - a , b , c , d , e , f , g , h , Finish Duration: 0 days, 1
Test Name: Start a b c d e f g h Finish
Duration: days, days?, days?, days?, days?, days?, days?, days?, days? days
Optimistic Duration: days, days, days, days, days, days, days, days, days, days
Expected Duration: days, days, days, days, days, days, days, days, days, days
Pessimistic Duration: days, days, days, days, days, days, days, days, days, days
Predecessors:
Project Model using MS Project
Given the project model above, and the simulation data table on the next page:
Calculate and identify the:
a median duration
b mean duration
c probability of completing the project in less than days
d critical index for each activity
e critical index for each path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
