Question: Test Practice Questions Session 7: Introduction to Project Planning and Network Analysis using PDM (AON) 6. 1. Briefly describe the term Work Breakdown Structure (WBS)

Test Practice Questions Session 7: IntroductionTest Practice Questions Session 7: Introduction

Test Practice Questions Session 7: Introduction to Project Planning and Network Analysis using PDM (AON) 6. 1. Briefly describe the term Work Breakdown Structure (WBS) and how would you create a WBS for a Project using an example 2. What are the key functions of a WBS? 3. Briefly explain the process of integrating Cost Breakdown Structure (CBS) and Organisational Breakdown Structure (OBS) with WBS 4. State the benefits of integrating WBS, OBS and CBS together in Project Management 5. What is a Linked Bar (Gantt) Chart? Use an appropriate sketch to explain your answer What are the two major categories of Scheduling Network Analysis? Briefly explain the difference between the two types of analysis 7. What are the key rules needed to be used when creating AON (Precedence diagram - PDM) logic- network? 8. What is a preceding activity? 9. What are the key elements would you estimate during the Network Analysis? 10. Define the following terms used in Network Analysis a. Dummy Activity b. Total Float 11. How would you identify a Critical Activity and the Critical Path during the Network Analysis? 12. What are the Four (4) Lag Factors? Briefly explain them using examples 13. Perform and estimate the following using PDM (AON) Network Analysis Draw the PDM network showing lag factors b. Calculate the earliest and latest event times. C. Calculate the total float times of each activity d. Define the critical path. State the overall project time. a. A. ID Duration Lag A B 5 10 Finish-to-Start Finish-to-Start Predecessor Lag None 0 A 0 A 0 B 5 C D 15 5 Additional Lag Relationship None None Start-Start C to D Start-Finish D to E Finish-Finish D to E Finish-Finish Eto F None Finish-Finish G to F None 0 0 20 5 25 0 0 10 0 0 E F G H 20 15 10 B D 0 10 0 20 F B. ID Duration Additional Lag Relationships Lag Finish-to-Start Predecessor None 0 1 A B C D E F 8 7 6 8 A B None Finish-Start B to E None None Finish-Start E to ] Start-Start F to H Start-Start G to 1 ITIL 5 8 7 0 0 5 6 2 C D E G G 10 9 H 1 J K None None Finish-Finish to K None None None Hand 1 0 0 1 3 5 0 C. ID Duration Lag Additional Lag Relationships None 0 A B C D 5 10 15 5 Finish-to-Start Finish-to-Start Lag Predecessor None 0 A 0 A 0 B 5 None 0 20 5 25 0 0 10 0 20 E F G H Start-Finish C to D Start-Start D to E Finish-Finish D to E Finish-Finish E to F None Finish-Finish G to F None B D F 15 5 0 0 10 14 0 D. ID Duration Lag Finish-to-Start Predecessor None A B 5 10 0 10 5 10 10 C D E F G H 10 15 15 10 4 Finish-to-Start Additional Lag Lag Relationship 0 None 0 Start-Start B to C Start-Start B to D Finish-Finish C to E 0 Finish-Finish D to E 0 None 0 Start-Finish F to G 0 Finish-Finish G to 5 Finish-Finish H to 1 0 None None None B E D C F 0 0 5 5 10 10 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!