Question: THANK YOU FOR YOUR HELP, WILL LIKE ! Table 12-3 Immediate Predecessor Pessimistic Activity A B Optimistic 4 12 Most Likely 5 16 6 18

THANK YOU FOR YOUR HELP, WILL LIKE !THANK YOU FOR YOUR HELP, WILL LIKE ! Table 12-3

Table 12-3 Immediate Predecessor Pessimistic Activity A B Optimistic 4 12 Most Likely 5 16 6 18 14 5 Standard Deviation 0.333 1.000 2.000 0.000 0.333 Variance 0.111 1.000 4.000 0.000 0.111 A 2 8 D 5 A B,C 5 7 E 6 8 4) According to Table 12-3, there are five activities in a PERT project. Calculate the task durations, then solve and plot the critical path