Question: The 3-point estimates for a projects tasks, and predecessor relationships are given in the table below. Complete the two empty columns. [5 points] Determine the
The 3-point estimates for a projects tasks, and predecessor relationships are given in the table below.
- Complete the two empty columns. [5 points]
- Determine the critical path and all activity slacks. [5 points]
- What is the expected project duration (TE)? [5 points]
- What is the probability of completing the project in 63 periods or less? Provide full analysis. [5 points]
- What project duration should be negotiated with the customer to expect 99% likelihood of on-schedule delivery? Provide full analysis. [5 points]
[Recommended time: < 20 minutes]
1.
| ID | Predecessor | to | tm | tp | te | Var |
| 1 | None | 5 | 8 | 17 | ||
| 2 | 1 | 3 | 4 | 17 | ||
| 3 | 1 | 7 | 11 | 21 | ||
| 4 | 2,3 | 5 | 6 | 13 | ||
| 5 | 3 | 3 | 4 | 11 | ||
| 6 | 1,5 | 7 | 12 | 23 | ||
| 7 | 4,6 | 11 | 17 | 29 | ||
| 8 | 7 | 2 | 4 | 6 |