Question: The above table is a sample and only shows the cycle for 10 batches. Having worked this out, we can calculate our maximum number of

The above table is a sample and only shows the cycle for 10 batches. Having worked this out, we can calculate our maximum number of batches as below: Businesshours - time taken Timetaken ('bake 1 stbatch) bakeeach subsequentbatch after the 1 st Timetaken & bake 1 st batch + () . 240 -26 minutes + 26 minutes= 214 minutes =22.4 batches 10 minutes 10 minutes