Question: The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide whether to use: the critical rule, the

The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide
whether to use: the critical rule, the order slack rule, the shortest operation next rule or the slack per operation rule.
The table below shows the companys current inventory and shop status.
Exhibit 1
Order number
Manufacturing
Lead Time
Remaining
Time Remaining
Until Due Date
Current
Operation
Processing Time
1
15
7
Number of
Operations
Remaining
Total Processing
Time Remaining
2
2
15
11
3
8
3
3
20-2
4
8
5
4
15-5
2
8
4
5
15
3
1
3
12
8
Note: Time is measured in days. Manufacturing lead time remaining includes both the machine processing time and the length of time orders
spend moving and waiting to be processed in a machine queue. Current operating processing time (as well as total processing time remaining)
includes no move or queue times.
8
a) State the formula for calculating the priority index for each of sequencing rules given above.
b) Compute the scheduling priority index for each order in Exhibit 1 for the four sequencing rules.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!