Question: The activities described by the following table are given for the Duplaga Corporation. Activity Time Immediate Predecessor ( s ) A 9 9 minus B

The activities described by the following table are given for the Duplaga Corporation.
Activity
Time
Immediate Predecessor(s)
A
99
minus
B
77
A
C
33
A
D
66
B
E
99
B
F
44
C
G
66
E, F
H
55
D
I
33
G, H
This exercise contains only part a.
Part 2
a) For the project, the Activity-on-Node (AON) LOADING... PERT LOADING... diagram is shown in