Question: The activities described by the following table are given for the Duplaga Corporation. Activity Time Immediate Predecessor ( s ) A 9 9 minus B
The activities described by the following table are given for the Duplaga Corporation.
Activity
Time
Immediate Predecessors
A
minus
B
A
C
A
D
B
E
B
F
C
G
E F
H
D
I
G H
This exercise contains only part a
Part
a For the project, the ActivityonNode AON LOADING... PERT LOADING... diagram is shown in