Question: The activities described by the following table are given for a construction project: Activity Time Immediate Predecessor(s) A 9 B 7 A C 3 A
The activities described by the following table are given for a construction project: Activity Time Immediate Predecessor(s) A 9 B 7 A C 3 A D 6 B E 9 B F 4 C G 6E, F H 5 D I 3G, H For the project, the longest procession path and total time would be? A, B, E, G, I = 34 A, B, D, H, I = 30 A, B, D, H, I = 38 A, C, F, G, I = 25
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
