Question: The activities described by the following table are given for the Howard Corporation in Kansas: Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks)
The activities described by the following table are given for the Howard Corporation in Kansas:
Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks) Immediate Predecessor(s) A 10 - D 6 B G 6 E, F B 6 A E 10 B H 6 D C 3 A F 10 C I 2 G, H
b) The activities on the critical path are