The activities of an IT project have the durations (in months) and dependencies as shown in Table1.
Question:
The activities of an IT project have the durations (in months) and dependencies as shown in Table1. Assume that the planned start date of the project is Sunday 1 August 2021.
Activity | Description | Predecessor | Duration in Months |
Planning | |||
A | Problem Definition | - | 1 |
B | Statement of Scope and Objectives | - | 1 |
C | Feasibility Study | - | 2 |
Analysis | |||
D | ERD | A, B, C | 9 |
E | Context Diagram, and DFD | A,B, C | 6 |
Design | |||
F | Physical Database Design | D | 3 |
G | Graphical User Interface | F | 6 |
Implementation | |||
H | Implementation and S/W Testing | F, G | 15 |
I | Installing the network and Network Security | H | 3 |
Testing | |||
J | System Acceptance Testing | I | 3 |
Table1
- Draw a network diagram using Ms. Project Management or Project liber for this project showing on the diagram the duration of each activity, predecessor, the earliest start, earliest finish, latest start, and latest finish dates, the free float, and the total float.
- What is the expected total duration of the project?
- What is the critical path? Display the critical path only in red color using the S/W.
- Insert the following human resources needed to implement the project as shown in table2.
Human Resource | Standard rate | Overtime rate |
Project Manager (PM) | $30/Hr | $35/Hr |
Systems Analyst and Designer (SAAD) | $22/Hr | $27/Hr |
Web Designer (WD) | $23/Hr | $28/Hr |
Software Developer (SD) | $20/Hr | $25/Hr |
Database Administrator (DBA) | $23/Hr | $28/Hr |
Software Tester (ST) | $21/Hr | $26/Hr |
Network Specialist (NS) | $21/Hr | $26/Hr |
Network Security Specialist (NS) | $23/Hr | $28/Hr |
System Integrator (SI) | $23/Hr | $28/Hr |
Table2
- Populate each task with the corresponding human resources who is going to be working on each task as shown in table3.
Activity | Description | HR |
Planning | ||
A | Problem Definition | PM |
B | Statement of Scope and Objectives | PM and SAAD |
C | Feasibility Study | PM |
Analysis | ||
D | ERD | SAAD |
E | Context Diagram, and DFD | SAAD |
Design | ||
F | Physical Database Design | SAAD, and DBA |
G | Graphical User Interface | SAAD, and WD |
Implementation | ||
H | Implementation and S/W Testing | SD, and ST |
I | Installing the network and Network Security | NS, and NSS |
Testing | ||
J | System Acceptance Testing | SI, ST, and SD |
Table3
- Calculate through the S/W the total required time, and the cost of every phase of the System Development Life Cycle (SDLC).