Question: The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. Activity Optimistic (a) Most Likely (m) Pessimistic (b) A 3
The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.
| Activity | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
|---|---|---|---|
| A | 3 | 4 | 7 |
| B | 5 | 10 | 12 |
| C | 5 | 7 | 17 |
| D | 4 | 6 | 9 |
| E | 3 | 5 | 13 |
| F | 4 | 6 | 10 |
| G | 3 | 4 | 7 |
| H | 5 | 7 | 8 |
Use the above information to do your analysis in the next question.
1)What is the expected time (te) for each activity? Round your calculations to the nearest second decimal point.
What is the critical path, and how long is this project expected to last
What is the variance of the critical path? Round your calculations to the nearest second decimal point.