Question: The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. Activity Optimistic (a) Most Likely (m) Pessimistic (b) A 3

The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.

Activity Optimistic (a) Most Likely (m) Pessimistic (b)
A 3 4 7
B 5 10 12
C 5 7 17
D 4 6 9
E 3 5 13
F 4 6 10
G 3 4 7
H 5 7 8

Use the above information to do your analysis in the next question.

What is the expected time (te) for each activity? Round your calculations to the nearest second decimal point. Show all your work.

What is the critical path, and how long is this project expected to last? Show all your work.

What is the variance of the critical path? Round your calculations to the nearest second decimal point.

Suppose you have a personal goal of completing this project in 31 weeks.

Use the above information to do your analysis in the next question.

What is the probability that you will be able to meet this goal? Round your analysis to the nearest second decimal point. Show all your work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!