Question: The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. ActivityOptimistic (a)Most Likely (m)Pessimistic (b) A 3 4 B 5


The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. ActivityOptimistic (a)Most Likely (m)Pessimistic (b) A 3 4 B 5 10 12 7 17 D 4 6 9 F 3 5 13 F 4 6 10 G 4 7 H 5 8 Use the above information to do your analysis in the next question. 1)What is the expected time (te) for each activity? Round your calculations to the nearest second decimal point. What is the critical path, and how long is this project expected to last What is the variance of the critical path? Round your calculations to the nearest second decimal point
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
