Question: The AOA network for a certain project is given in the graph below with the task durations ( in days ) in the table beneath

The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The activities d1 and d2 are dummy activities.
How many paths are there from start to finish?
4
5
6
3
None of the other options are correct
The AOA network for a certain project is given in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!