Question: The AOA network for a small project is shown below with activities' names shown on top of arrows and their duration in the bottom. Perform

The AOA network for a small project is shown below with activities' names shown on top of arrows and their duration in the bottom. Perform the followings: a. Compute the early start (ES), early finish (EF), late start (LS), late finish (LF), and total float (TF) times for each activity in a table; b. Show the critical path(s) on the figure