Question: The AON diagram is provided, label them correctly ( 1 % ) ( 2 % ) find critical path by using forward and backward pass
The AON diagram is provided, label them correctly
find critical path by using forward and backward pass Answer: same as N
find the length of the project Answer: same as K
What is the possibility to finish the project in weeks? Answer same as R
What is the due date that guarantee chance of ontime completion? Answer same as T
Time estimates weeks
Activity Predecessors Optimistic Most likely Pessimistic Expected values Variance ES EF LS LF LE Start LE Finish Critical path Variance Stdev "Finsih in
weeks Z score?"
A
B
C
D BC
E AD
F C
G CEF
H F
I FGH
J G I