Question: The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The

The AON diagram shown represents a project.The AON diagram shown represents a project.

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The project duration should be shorten one day. Which activity should be crashed one day? a. 1 b. 2 c. 3 d. 4 e. 5 f. 6 g. 7 h. 8 i. None of them. It is impossible to crash the project