Question: The A-O-N network diagram and time estimates (in days) of each activities for the custom order project of the Air Control Company is presented
The A-O-N network diagram and time estimates (in days) of each activities for the custom order project of the Air Control Company is presented below. 0 Start 0 D Z= FORMULAE Activities a+4m+b A B T-T ot C D E F a Optimistic Time Most Likely Time 15 5 16 12 D 1 1 C P. O = (P=), TE = . OTg = m 18 11 28 15 4 4 F E Pessimistic Time b 27 critical path? (5 points) e) What is the probability that the project will finish before 48 days? (5 points) f) What is the probability that the project will finish before 52 days? (5 points) 23 a) Calculate the expected time of each activity? (5 points) b) Calculate the variance of the time for each activity? (5 points) c) Find the critical path. What are the activities on the critical path? (5 points) d) What is the expected completion time of the Project and what is the standard deviation of 46 18 13 7 Z value End 0.22 0.32 0.62 0.97 1.12 1.27 10 Probability 0.59 0.63 0.73 0.83 0.87 0.90
Step by Step Solution
3.56 Rating (156 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
