Question: The basic management functions are: Select one: O a. Organizing b. Leading O c. All are true O d. Planning If you know that your




The basic management functions are: Select one: O a. Organizing b. Leading O c. All are true O d. Planning If you know that your project has 5 major activities and 3 sub activities, what would be the number of milestone: Select one: a. 3 Milestones O b. 8 Milestones O c. All are true O d. 5 Milestones N If you know that milestone 1 will begin on 1st May while milestone 2 will begin on 1st of July, what would be the end M1: Select one: a. 30th July b. 30th Jun O c. 1st May O d. None is true Ne If you have 3 paths ABC 15 days, ACE 12 days ACF 18, what path would be the critical path: Select one: o a. ACE O b. ABC O c. All are true O d.ACF