Question: The Bookworm Paper Manufacturing Ltd intends to install a computerized air pollution control equipment in its facility, as per project activities, durations and precedence relationships
- The Bookworm Paper Manufacturing Ltd intends to install a computerized air pollution control equipment in its facility, as per project activities, durations and precedence relationships shown below:
| ID | Description | Predecessor | Time (Weeks) |
| A | Build internal components | 2 | |
| B | Modify roof and floor | 3 | |
| C | Construct collection stack | A | 3 |
| D | Pour concrete and install frame | A,B | 4 |
| E | Build high-temperature burner | C | 4 |
| F | Install pollution control system | C | 3 |
| G | Install air pollution device | D,E | 5 |
| H | Inspect and test | F,G | 2 |
- Draw the project network showing activity early, late, and slack times. [16 marks]
- List all merge and burst activities on the network. [3 marks]
- Indicate the various paths and determine the critical path. [3 marks]
- What is the duration of the project? Since this is a flagship sustainability project, the CEO of the organization wants to commission the plant on World Environment Day, which is exactly 14 weeks away. Will the project be ready by then? [3 marks]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts