Question: The budget for each work package is ______. A. charged completely on the first day of the work package B. charged at the end of
The budget for each work package is ______.
A. charged completely on the first day of the work package
B. charged at the end of the project
C. distributed over the duration of the work package
D. charged completely on the last day of the work package