Question: The budget for each work package is: Question 39 options: distributed over the duration of the work package. charged completely on the first day of
The budget for each work package is: Question 39 options: distributed over the duration of the work package. charged completely on the first day of the work package. charged at the end of the project. charged completely on the last day of the work package.Equipment costs in the project costs estimate are for equipment: Question 40 options: that the organization wants to have. that must be purchased as part of the project. that is the latest upgrade, even if not needed for the project. needed by others in the organization that may not be assigned to the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
