Question: The But-for or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of delays without

The "But-for" or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of delays without any consideration of the As-planned schedule. true or false