Question: QUESTION 6 The But-for or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of
QUESTION 6
-
The "But-for" or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of delays without any consideration of the As-planned schedule.
True
False