Question: The construction project that the team has been working on for a couple years is coming to a close. Individuals have been working to keep
The construction project that the team has been working on for a couple years is coming to a close. Individuals have been working to keep solid notes on the things that have gone well and gone poorly, and they wish to share these notes with one another. During the session, these notes are recorded and then will be retained by the project manager in which resource?
Retrospective
B Lessons learned register
C Iteration log
Lessons learned repository