Question: The Contractor has left the direct fee percentage entry blank. You speak to the Contractor about this and you are told that, it thought Contract
The Contractor has left the direct fee percentage entry blank. You speak to the Contractor about this and you are told that, it thought Contract Data part two had been completed properly, but nevertheless it should be 11% and the Contractor now wants to include this in Contract Data part two. You are told, verbally, that 'in a spirit of mutual trust and co-operation' you should agree.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Contractual Guidance on Changes to Contract Data In construction contracts particularly under standard forms such as the JCT or NEC the Contract Data is a key document that outlines specific terms inc... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
