Question: The cost and schedule data for a building project are detailed in the following table. Assume an indirect cost $900 per da. What is the

The cost and schedule data for a building project are detailed in the following table. Assume an indirect cost $900 per da. What is the optimum (least cost) duration for the project?

Activity Preceded By Cost Duration
Crash Normal Crash Normal
A - 3,100 2,500 5 6
B - 8,200 7,000 7 10
C B 7,000 6,500 5 6
D - 11,800 10,000 10 12
E A 5,700 4,200 9 12
F C, D 8,500 8,200 5 6
G E,F 6,000 5,200 4 5
H C,D 8,700 7,500 5 8
I G,H 6,000 5,600 3 4