Question: The cost and schedule data for a building project are detailed in the following table. Assume an indirect cost $900 per da. What is the
The cost and schedule data for a building project are detailed in the following table. Assume an indirect cost $900 per da. What is the optimum (least cost) duration for the project?
| Activity | Preceded By | Cost | Duration | ||
| Crash | Normal | Crash | Normal | ||
| A | - | 3,100 | 2,500 | 5 | 6 |
| B | - | 8,200 | 7,000 | 7 | 10 |
| C | B | 7,000 | 6,500 | 5 | 6 |
| D | - | 11,800 | 10,000 | 10 | 12 |
| E | A | 5,700 | 4,200 | 9 | 12 |
| F | C, D | 8,500 | 8,200 | 5 | 6 |
| G | E,F | 6,000 | 5,200 | 4 | 5 |
| H | C,D | 8,700 | 7,500 | 5 | 8 |
| I | G,H | 6,000 | 5,600 | 3 | 4 |