The schedule, duration, and cost data for a small building project are detailed in the following table. Assume an indirect cost of $120 per day.
Activity Immediately preceding activity normal duration Crash duration Normal cost Crash cost
A -54770900
B -32660700
C A 748001,070
D A, B 431,0001,110
E B 64800920
F C, D 65560630
G D 53700810
H F 841,0001,260
I
E, G 43500580
J
H, I 32400600
What is the cost associated with the crash duration of the project? Answer: ______ dollars.