Question: The critical path ______________. A is the longest path through the network diagram B is the shortest path through the network diagram C always has
The critical path ______________.
A
is the longest path through the network diagram
B
is the shortest path through the network diagram
C
always has zero float
D
method utilizes buffers to manage float
_______ is a schedule compression technique in which sequentially scheduled activities are performed in parallel instead.
A
Leads
B
Crashing
C
Fast tracking
D
Resource leveling