Question: The critical path calculation shows B - D - E - F - H is the critical path, and the expected project completion time is

The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 31 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:
Formulate a linear programming model that can be used to make the crashing decisions for this project. If necessary round your answers to the nearest dollar. If the constant is "1" it must be entered in the box. If your answer is negative value enter minus sign. 