"The critical path consists of the sequence of activities that must be completed in order to finish the project in the shortest possible time. Any delay in activities along the critical path will directly impact the project's overall duration." The critical path identifies the least amount of time that it would take to complete will project and it also notes the longest amount of time that it takes to finish the project. Thoughts?