Question: The critical path for the network activities shown above is _ _ _ _ _ _ _ _ _ _ with duration _ _ _

The critical path for the network activities shown above is__________ with duration__________.
Part 2
A.
AminusBminusD; 10
B.
AminusBminusCminusDminusE; 22
C.
AminusDminusE; 13
D.
CminusE; 12
E.
AminusBminusE; 11