Question: The critical path for the network activities shown below is duration table [ [ Activity , Duration,Predecessors ] , [ A , 4 ,

The critical path for the network activities shown below is duration
\table[[Activity,Duration,Predecessors],[A,4,-],[B,2,A],[C,7,-],[D,4,A],[E,5,B,C,D]]
A-B-D; 1
A-B-E; 11
C-E; 12
A-D-E; 13
A-B-C-D-E; 22