Question: Q 1 . The critical path for the network activities shown below is duration table [ [ Activity , Duration, table [ [

Q1. The critical path for the network activities shown below is duration
\table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,4,--],[B,2,A],[C,9,--],[D,4,A],[E,5,B,C,D]]
A) A-B-D; 10
B) A-B-E; 11
C) C-E; 14
 Q1. The critical path for the network activities shown below is