Question: - The critical path for the network activities shown below is ________ Activity Duration Immediate Predecessors A 4 -- B 2 A C 9 --
- The critical path for the network activities shown below is ________
Activity Duration Immediate Predecessors
A 4 --
B 2 A
C 9 --
D 4 A
E 5 B,C,D
Select one:
a.
A-B-C-D-E
b.
A-B-D
c.
A-D-E
d.
C-E