Question: The critical path for the network activities shown below is __________ with duration __________. a. V-W-Z; 23 b. V-X-Z; 17 c. V-X-Y-Z; 21 d. V-X-W-Y-Z;

The critical path for the network activities shown below is __________ with duration __________.

The critical path for the network activities

a.

V-W-Z; 23

b.

V-X-Z; 17

c.

V-X-Y-Z; 21

d.

V-X-W-Y-Z; 29

e.

none of the above

Activity Duration | V W x Y Z 10 8 2 4 5 Immediate Predecessors -- V V X W, Y