Question: Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of

Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of 13 days. What is the expected duration of activity D?

Formula: Expected Activity time: t = (a + 4m + b)/6

a.

5 days

b.

6 days

c.

7 days

d.

10 days

e.

12 days

The critical path for the network activities shown below is __________ with duration __________.

a.

V-W-Z; 23

b.

V-X-Z; 17

c.

V-X-Y-Z; 21

d.

V-X-W-Y-Z; 29

e.

none of the above