Question: Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of
Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of 13 days. What is the expected duration of activity D?
Formula: Expected Activity time: t = (a + 4m + b)/6
| a. | 5 days
| |
| b. | 6 days
| |
| c. | 7 days
| |
| d. | 10 days
| |
| e. | 12 days |
The critical path for the network activities shown below is __________ with duration __________.
| a. | V-W-Z; 23 | |
| b. | V-X-Z; 17
| |
| c. | V-X-Y-Z; 21
| |
| d. | V-X-W-Y-Z; 29
| |
| e. | none of the above |