Question: The critical path for the network activities shown below is with duration Select one:a . A - D - E; 1 3 b . A

The critical path for the network activities shown below is with duration
Select one:a. A-D-E; 13b. A-B-C-D-E; 22c. C-E; 12d. A-B-E; 11e. A-B-D; 10