Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 -- B 4 -- C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 2 | -- |
| B | 4 | -- |
| C | 6 | A,B |
| D | 1 | A,B |
| E | 2 | B,C,D |