Question: The critical path has five activities in a CPM network. their durations are tabulated next. Find: table [ [ Duration ( Days ) ]

The critical path has five activities in a CPM network. their durations are tabulated next. Find:
\table[[Duration (Days)],[Activity,To,Tm,TP,],[A,4,6,9,],[D,6,10,15,],[G,7,11,15,],[H,10,20,36,],[M,8,10,14,],[O,4,5,8,]]
The duration of the project with its standard deviation
(5%)
The probability that the project will be finished by the end of day 65
(2%)
The probability that the project will finish before day 60
(2%)
The probability that the project will finish on the 62nd day
(2%)
The probability that the project will finish at least six days early
(2%)
6. The completion date with at least a 95% confidence level
(2%)
The critical path has five activities in a CPM

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!