Question: The critical path in a project network is the Question 9 options: longest path through the network. network path with the most difficult activities. network

The critical path in a project network is the
Question 9 options:
longest path through the network.
network path with the most difficult activities.
network path using the most resources.
shortest path through the network.
network path with the most merge activities