Question: The critical path is defined as: ( select all that apply ) The path that gives the shortest duration to complete the project. A path
The critical path is defined as: select all that apply
The path that gives the shortest duration to complete the project.
A path for which none of the activities can be delayed without compromising the duration of the project. A path where all activitics have no floats.
A path where some activities have floats.
The longest path in the network diagram in terms of duration.