Question: the critical path should also be determined. Here are the activity times. table [ [ , , , , , ] , [ Activity
the critical path should also be determined. Here are the activity times.
tableActivityTime weeks Immediate PredecessorsActivity,Time weeks Immediate PredecessorsAEBBFBCAGC EDAHD F
Dave's earliest start ES and earliest finish EF are:
tableActivityESEFA