Question: The customer is looking for the project to be complete 10 days earlier than planned due to marketing constraints. You work with your project team

The customer is looking for the project to be complete 10 days earlier than planned due to marketing constraints. You work with your project team and figure out that this can be achieved if a couple of activities can overlap. This approach is known as? a Fast Tracking b Crashing c Resource Leveling d Concurrent Engineering